MPI Offshore Limited installed all 27 turbines at Inner Dowsing using the purpose-built turbine installation vessel MV Resolution, completing the work by mid-2008 alongside the twin Lynn campaign (54 turbines combined). MV Resolution also installed the monopile foundations under MT Højgaard's foundation contract.