Foundation installation at Inner Dowsing began in 2007 under MT Højgaard's contract using the MPI Resolution heavy-lift jack-up vessel. The campaign drove 27 monopile foundations into the seabed approximately 5.2 km off the Lincolnshire coast as part of the combined Lynn + Inner Dowsing programme (54 monopiles total). Foundation works completed by end-2007; cable and turbine installation followed through 2008, with full commercial operations from March 2009. Year precision used as exact start month is not pinned in publicly available sources.