Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The commencement of Inch Cape’s offshore transmission infrastructure construction is defined as the start of licensable works at the Cockenzie landfall, with nearshore civil and cable‑protection activities expected from April 2025 and, by mid‑2025, contractor Charles Brand already removing and rebuilding a section of seawall and installing ducts to bring the export cables ashore adjacent to the new substation.