Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of Inch Cape's wind turbine foundations commenced in December 2025 when the first XXL monopiles arrived at the Port of Leith in October 2025, fabricated by CWHI (GWSHI) and Dajin Offshore, and the first monopile was installed at the offshore site in December 2025 by Jan de Nul. The 1,080 MW wind farm will use a mix of monopile and jacket foundations across 72 turbine positions. The first transition pieces arrived at Leith in January 2026 and the first jacket foundations arrived in March 2026, with Seaway 7 contracted for jacket installation using the Seaway Alfa Lift vessel.