Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2025, at the Cockenzie landfall adjacent to the under‑construction onshore substation, contractor Charles Brand has been carrying out major civil works for the offshore transmission landfall, including removing and rebuilding a 35‑metre section of seawall, installing ducts for the two export cables, and restoring the foreshore and diverted John Muir Way, with landfall works programmed between April and September 2025.