By 23 October 2025, Inch Cape had successfully installed the first of its two 85‑kilometre, 220 kV three‑phase offshore export cables, laid in three roughly 28‑kilometre sections by Enshore Subsea’s CMOS Installer vessel from the Port of Blyth, with two offshore joints completed using North Sea Giant to link the offshore substation platform to the new onshore substation at Cockenzie.