Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
TenneT’s blog article "Milestone Land station Maasvlakte in the spotlight" (published 13-2-2025) states that, after completing the hall and converter station for IJmuiden Ver Beta, "work on the connection for IJmuiden Ver Gamma is set to begin in the first quarter of 2026." This is taken as the start of onshore construction for the IJmuiden Ver Gamma grid connection.