Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Windpowernl, citing TenneT project manager Maurice Olijerhoek, reports that from February 2026 construction consortium NRG will begin installing the onshore HVDC cables underground for the IJmuiden Ver Alpha and Nederwiek 1 grid connections, along the route from De Piet harbour (Arnemuiden) to the converter stations in the Sloe industrial zone. This marks the start of onshore construction works for the IJmuiden Ver Alpha grid connection.