Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In early August 2024, TenneT began onshore construction for the Net op zee IJmuiden Ver Alpha grid connection at Borssele by driving the first foundation pile for the onshore converter station into the ground, officially marking the start of the first 2 GW connection. The converter station at Borssele forms a key part of the underground high-voltage link that will transport offshore wind power from IJmuiden Ver Alpha to the existing onshore grid.