Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DELAYED +2yr (Apr 2026): TenneT’s official Net op zee Zeeland planning shows the first offshore jacket installation for IJmuiden Ver Alpha in spring 2027; there is no evidence that offshore grid construction started in early 2025, so the offshore_construction_start is shifted to spring 2027, later than the original 2025 plan. --- DEME was awarded contracts by Prysmian to execute engineering and installation works for TenneT’s IJmuiden Ver Alpha offshore grid connection, including cable installation, landfalls, dredging, rock placement, beach works and cofferdam structures, with these offshore and nearshore construction activities scheduled to begin in stages from 2025.