By 9 January 2026, Prysmian had completed manufacturing and delivered 63 large reels of onshore land cables to Verbrugge Terminals in Vlissingen-Oost for TenneT’s IJmuiden Ver Alpha and Nederwiek 1 grid connections, marking the end of more than two and a half years of design, testing and production of the minus, plus and earth cables that will connect the offshore wind areas to converter stations in the Sloe industrial zone.