Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
DELAYED +5mo (Apr 2026): Geophysical survey start was set at 1 Jan 2026. NextGeo’s July 2025 communications (Ocean News & Technology and WindpowerNL) for IJmuiden Ver Alpha and Nederwiek 1 confirm that marine survey services, including geophysical investigations and UXO surveys, are planned between 2026 and 2027. This contradicts a hard 1 Jan 2026 start and instead indicates a 2026–2027 execution window, so the start date is adjusted to mid‑2026. --- Prysmian awarded Next Geosolutions (NextGeo) a contract to carry out export cable route geophysical surveys for the IJmuiden Ver Alpha and Nederwiek 1 offshore grid connections, with survey work along the cable routes scheduled to start in 2026 and run through 2027 to support the final design of TenneT’s 525 kV XLPE HVDC cable systems landing at Sloegebied in Zeeland.