Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Planning documentation recorded that the UXO licences covering IFA2 activities had expiry dates in December 2020 and therefore stated UXO survey/clearance works for the project were to be completed by December 2020. The record indicated UXO activities for both DC and AC cable redlines would be finished before the commencement of later construction phases.