Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The French Energy Regulatory Commission (CRE) approved the IFA2 project and defined the incentive regulation regime on 2 February 2017. CRE’s deliberation approved RTE’s involvement and linked the incentive regime to the requirement that RTE take its final investment decision before 31 December 2018 to benefit from the defined regulatory treatment.