Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The IFA2 cable installation campaign concluded in January 2020 after the subsea cable-lay programme that ran through 2019. Post-lay activities identified some sections requiring remedial burial work; the developer carried out further burial and post-lay surveys and used a risk allowance to address remediation and cable protection where necessary. The completion of the cable-laying phase preceded later commissioning and the project’s entry into commercial operation in January 2021.