Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Horizontal directional drilling for the Humber Gateway export cable landfall ducts was completed in Q1 2012 by Stockton Drilling Limited, providing the shore-crossing infrastructure needed for the 132 kV export cables to come ashore and link to the onshore cable route.