Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Ørsted’s DCO examination submission includes an indicative programme (Table/graphic) stating “Hornsea Four Foundations. 2026”. Since Ørsted later discontinued Hornsea 4 “in its current form” (terminating supply-chain contracts and not delivering under the AR6 CfD) on 2025-05-07, the 2026 timeline is stale; shifting +4 years to reflect the project being pushed beyond the original pre-FID plan, giving a projected foundation installation start in 2030.