Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Ørsted’s Hornsea Four DCO examination roadmap states an indicative milestone “First Power (partially operational windfarm). 2028”. Ørsted subsequently discontinued Hornsea 4 in its current form on 2025-05-07 (not delivering under the AR6 CfD and terminating supply-chain contracts), making the 2028 first-power target stale; shifting the indicative date +4 years gives a projected first power in 2032.