Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By May 2018, Ørsted Hornsea Project Three (UK) Ltd had secured a Grid Connection Agreement for Hornsea 3, confirming a connection point at the Norwich Main 400 kV substation between Swardeston and Stoke Holy Cross in South Norfolk, with the connection envisaged for 2023/2024. This agreement establishes access to the UK National Grid for the project’s export capacity via the planned HVDC/HVAC transmission system and associated onshore infrastructure.