Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In Ørsted’s Q3 2025 investor presentation, the company states that for Hornsea 3 it plans, in the coming period, to complete the onshore export cable and install the offshore export cable, followed by energisation of the offshore converter station, initiating system testing and commissioning activities for the HVDC transmission link.