Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction on the Hornsea 3 transmission system effectively started in Q1 2025 when installation of the offshore export cables commenced along the Offshore Export Cable Corridor between the two offshore converter stations and the landfall at Weybourne Beach, Norfolk. The Safety Zone Application records that export cable installation began in Q1 2025 and is scheduled to continue through Q4 2026, forming the first major offshore construction activity for the project’s HVDC link.