Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By October 2020, archaeological investigations along the Hornsea Two onshore cable route between Horseshoe Point landfall and the onshore substation at North Killingholme were underway, supporting route preparation for the project’s transmission cables.