Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 29 April 2019, Royal Boskalis Westminster N.V. was awarded by Ørsted Wind Power A/S an offshore export cable installation contract worth more than EUR 100 million for Hornsea 2, covering route preparation, installation, and protection of three approximately 130 km export cable circuits (about 380 km total) that connect the offshore substation to the onshore substation via a horizontal directional drilling landfall crossing at Horseshoe Point, UK, for the project’s transmission link.