Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Ørsted's April 2021 Hornsea One and Two community newsletter reported that onshore substation construction at North Killingholme was largely complete, with all high-voltage equipment and underground cables installed and first phase of testing with the National Grid completed in February-March 2021, indicating commissioning around early 2021.