Tideway BV was awarded a design-and-build export cable installation contract for the Hornsea Project One offshore wind farm by DONG Energy. Tideway’s scope included cable-laying and seabed preparation works such as pre-trenching, backfilling, pre-sweeping, route preparation and rock placement for three high-voltage subsea export cables from the shore landfall near Horseshoe Point to three offshore substation platforms, as well as installation of two interlink cables. The offshore execution was planned to start with an engineering route survey in 2017 and continue through mid-2019.