Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 2 December 2019, UK‑based First Subsea Limited won a contract from the Van Oord–Hellenic Cables consortium to supply cable protection systems (CPS) for the Hollandse Kust Zuid export cables, including cross‑over protection. These CPS solutions support and protect the 220 kV export cable systems serving both the Alpha and Beta grid connections, thereby contributing to the integrity of the HKZ Beta export route to shore.