Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
As part of the Hollandse Kust (zuid) grid connection, TenneT built a new high-voltage substation and began expanding the existing Maasvlakte 380 kV substation, which will receive power from the HKZ Alpha and Beta 220 kV export cables and feed it into TenneT’s Randstad 380 kV South ring and the Dutch national high-voltage network.