Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 30 August 2021, DEME’s cable-laying vessel Living Stone had completed installation of the export cable connecting the Hollandse Kust Zuid Beta offshore platform to the Dutch mainland, as part of a campaign in which Living Stone installed two 34 km export cables and an 8 km interlink cable for the Hollandse Kust Zuid offshore grid.