Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 27 August 2025, Site Acceptance Tests for the Hollandse Kust West Beta transmission system had been successfully completed, covering two 220 kV export cable systems to shore and the 66 kV interconnector between the Hollandse Kust West Alpha and Beta platforms, thereby confirming grid readiness of the connection for the OranjeWind offshore wind farm.