TenneT’s HelWin2 (NOR-4-2) 690 MW VSC-HVDC grid connection underwent system commissioning around 2015. Under a contract worth over €200 million, Prysmian supplied, installed and commissioned the ±320 kV, ~130 km submarine and land cable system linking the Amrumbank West wind farm area in the HelWin cluster to the onshore converter station at Büttel, while Siemens provided the 690 MW Voltage Sourced Converter system; commissioning and commencement of commercial operation of the HVDC link were planned for 2015 and later reported with HelWin2 in operation from 2015.
HelWin2 grid connection system commissioned and operational.
In June 2014, the 10,500‑ton topside of the HelWin2 HVDC converter platform was loaded out from Heerema Fabrication Group’s yard at Zwijndrecht in the Netherlands for transport to its offshore site in the German Bight, marking a key construction milestone for TenneT’s 690 MW HelWin2 grid connection.
On 2 August 2011, TenneT awarded Prysmian a contract worth in excess of €200 million for the HelWin2 grid connection, covering the complete supply, installation and commissioning of the ±320 kV HVDC submarine and land cable system (about 85 km sea route plus 45 km land route) to the Büttel converter station, as well as 155 kV HVAC submarine cables linking the Amrumbank West offshore wind park transformer to the HelWin Beta offshore converter platform.
As part of an approximately €600 million consortium contract for the HelWin2 project awarded by TenneT, Siemens Energy was selected to supply the 690 MW HVDC Plus voltage-sourced converter system, providing converter equipment on the HelWin Beta offshore platform and at the onshore Büttel converter station to transmit power from the Amrumbank West wind park to the German grid.