The HVDC HelWin1 construction timeline on Grokipedia states that subsea cable laying for the 85 km offshore DC link followed installation of the HelWin alpha platform and "spanned late 2013 into 2014." This indicates that the export cable installation campaign began in late 2013, later than the originally projected 2012 start based on early logistics and storage of Prysmian export cables.