The offshore installation of the Helgolandkabel subsea power cable was completed in June 2009, when the cable‑lay vessel Nostag 10, having started work from St. Peter‑Ording on 6 June 2009, reached Helgoland after 12 days of laying the approximately 53‑kilometre cable, which was buried about 1.5 metres into the sandy seabed.