Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cadeler’s installation vessel Wind Orca installed the first Vestas V236-15.0 MW turbine at EnBW’s He Dreiht offshore wind farm on 24 April 2025, initiating the turbine installation campaign. This was the first commercial offshore installation of Vestas’s 15 MW model, with Wind Orca transporting components from Esbjerg and placing the turbines on pre-installed monopile foundations for the 960 MW project.