Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By 23 March 2023, EnBW had secured long-term power purchase agreements for around 335 MW of capacity from the 960 MW He Dreiht offshore wind farm, including contracts with Evonik (100 MW and 50 MW), Fraport (85 MW), Bosch (50 MW) and Salzgitter Flachstahl (50 MW); this portfolio builds on an 85 MW, 15‑year PPA with Frankfurt Airport operator Fraport that was signed in December 2021 and will start delivering power in 2026.