On 19 February 2026, EnBW recorded a construction milestone at its He Dreiht offshore wind farm in the North Sea when the installation vessel Wind Keeper replaced the Wind Orca as the dedicated turbine installation vessel. This change of vessel occurred during the main wind turbine installation phase, in which components are transported and lifted onto pre-installed foundations offshore. The construction diary notes that adverse weather conditions in the area were impacting offshore activities, meaning that despite the vessel change it would still take some time before Wind Keeper could fully install the first wind turbines at the He Dreiht site.