DELAYED +3mo (May 2026): Official EnBW communications frame completion as ‘by summer 2026’ rather than Q2: project page says ‘By summer 2026, all 64 wind turbines are scheduled to go onstream’, and EnBW’s Jan-2026 milestone press release also says commissioning completion ‘by the summer of 2026’. Given this summer (Q3) framing and recorded weather-related installation pauses, the prior Q2 (2026-06-30) full-COD projection looks optimistic; shifting to Q3 2026. --- Full commercial operation of the 960 MW He Dreiht offshore wind farm is planned for mid to late Q2 2026, with EnBW targeting completion of commissioning and COD after an initial start of commercial operations in early 2026. EnBW and market disclosures describe all 64 turbines being installed and commissioned by summer 2026, with the project then operating at full capacity to supply electricity to around 1.1 million households.