Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By 1 July 2025 Seaway7 had completed installation of all inter-array cables for EnBW’s 960 MW He Dreiht offshore wind farm, laying approximately 100 kilometres of 66 kV subsea cables to connect 13 strings of turbines to the BorWin epsilon converter platform. The campaign used the cable‑lay vessel Seaway Aimery and support vessel Seaway Moxie, which together laid and pulled in all 64 cables before moving on to trenching and final jointing works.