On 3 December 2019, the heads of Lithuanian and Polish transmission system operators Litgrid and PSE signed an agreement with the EU’s Innovation and Networks Executive Agency for EUR 10 million in Connecting Europe Facility support to fund preparatory work for the Harmony Link submarine interconnection, including route selection studies, seabed surveys, technical specifications, and spatial planning. Of this total, EUR 4 million was allocated to Lithuania.