Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 20 May 2020, survey contractor Next Geosolutions announced it had secured a contract from Svenska kraftnät to perform a complementary marine survey for the Hansa PowerBridge interconnector. Under the contract, Next Geosolutions is to carry out marine geophysical and geotechnical surveys offshore Sweden along the planned 300 km HVDC route between Güstrow in Germany and Sweden, supporting detailed development of the project.