Following the granting of planning approval for the German land and territorial sea sections of Hansa PowerBridge, 50Hertz indicated that, once the remaining permit for the German Exclusive Economic Zone is obtained from BSH and tenders for cables, converters and associated works are finalised, construction work on the interconnector would be able to begin in 2024. This planned start of implementation covers production and installation of the HVDC cables and construction of converter-related infrastructure between the Güstrow area and the Baltic Sea landfall at Dierhagen Ost.