On 28 October 2022, transmission system operators Svenska Kraftnät and 50Hertz decided to cancel the ongoing procurement process for the Hansa PowerBridge project due to changed technical requirements and challenges in the existing electricity network, announcing that procurement was likely to restart in the first quarter of 2024 and that the planned cable commissioning would be delayed from 2026 to 2028/29.