Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
The survey vessel Proteus of Liverpool began geophysical survey operations in and around the operational Gwynt y Môr offshore wind farm on 21 April 2017, as notified to mariners. The work involved geophysical surveying of the site area off the North Wales coast for the 576MW project comprising 160 Siemens 3.6MW turbines.