Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 23 April 2014, RWE’s jack-up installation vessel Friedrich Ernestine installed the 160th and final transition piece at Gwynt y Môr, completing installation of all 160 monopile-and-transition-piece foundations for the wind farm off the North Wales coast.