A further export cable repair campaign is planned for summer 2025 at Gwynt y Môr, involving replacement of a 5km section of 132kV export cable from the onshore transition joint bay towards the offshore platform near Abergele. N-Sea will execute the works using its cable repair vessel Curo, supported by anchor‑handling and support vessels, with offshore operations due to start on or around 22 July 2025 under Marine Licence CML1452v2.