Following the October 2020 export cable failure on the Gwynt y Môr OFTO link, repair works were carried out through to at least 31 March 2021, by which time costs exceeded £1 million. The campaign involved outages and interventions on the affected offshore cable section whose fault originated in a fibre‑optic component within the power cable.