Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In August 2007, Gwynt y Môr agreed and signed a Connection and Use of System Code (CUSC) bilateral agreement and a CUSC construction agreement with NGET for a grid connection at St Asaph, securing Transmission Entry Capacity of 735 MW for the project’s offshore transmission connection into the UK transmission system.