Gwynt y Môr OFTO completed the Stage 3 Repair of subsea export cable 3 (SSEC3) on 30 August 2024 under a contract signed on 16 May 2024 with a repair contractor (identified in project documentation as N-Sea), using two jack-up barges HavenSeaRiser 4 and HavenSeaSeven and associated vessels to replace and joint new 132 kV export cable between the transition joint bay and offshore, in a complex nearshore environment involving HDD ducts, beach quadrants and constrained joint bay space.