Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Greenlink Interconnector Limited signed a grid connection agreement with EirGrid for the Ireland-side connection at Great Island. The connection agreement (recorded as P 285 - AM - OL) documented the agreed technical interface and specified a nominal capacity of 500 MW for the interconnector; Greenlink described the signing as a key milestone enabling the project to progress towards construction.