Greenlink commenced pre‑construction geophysical surveys in September 2018. A Notice to Mariners (19 Sep 2018) and project communications confirmed MMT was contracted to carry out nearshore and offshore geophysical data acquisition off Baginbun Beach (and possibly Boyce’s Bay), with the objective of mapping seabed and shallow sub‑surface geology, informing cable routing and target burial-depth assessment, and providing data for marine archaeological assessment and consenting.