Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
The Western Nevada Master Plan identified Phase 1 (ISD 2025) of the Greenlink Nevada Transmission Project to increase TRIC capacity on the 120 kV system from 330 MW to 600 MW. Works specified for Phase 1 included the West Tracy–CMM 345 kV line and installation of the CMM 345/120 kV #1 280 MVA transformer. The master plan presented these items as the initial in‑service deliverables to strengthen transfer capacity and reliability for northern–southern Nevada power flows. The entry is documented in the ESIG master plan slides for Greenlink (ISD 2025).